Can you please check to see when the bridge is supposed to be completed and if they are currently on schedule? After doing some research, I found that construction for the new bridge …
This item is available in full to subscribers.
To continue reading, you will need to either log in to your subscriber account, below, or purchase a new subscription.
Please log in to continueDon't have an ID?Print subscribersIf you're a print subscriber, but do not yet have an online account, click here to create one. Non-subscribersClick here to see your options for subscribing. Single day passYou also have the option of purchasing 24 hours of access, for $1.00. Click here to purchase a single day pass. |
Can you please check to see when the bridge is supposed to be completed and if they are currently on schedule?
After doing some research, I found that construction for the new bridge over Little Black Creek is currently on schedule.
The old bridge was removed entirely, and the first bridge piles were reinstalled in June.
As of Aug. 12, the entire County Road 220 widening project, from Knight Boxx Road to Hollars Place, just west of the Henley intersection, was said to be 45% complete. And at that time, more than half of the new bridge deck had been poured. Drainage pipe installation is also continuing along CR 220.
The county advised that drivers should continue to expect lane closures and potential delays as the project progresses.
The project is expected to be completed by the end of 2026.
If you have a question about your community you would like answered, email kyla@claytodayonline.com.